Download 1 Memo of the meeting concerning the TV system of PITZ on Janury 25 2011
2 ----------------------------------------------------------------------
3
4 Participants:
5 J.Baehr, M.Gross,Y .Ivanisenko, M.Mahgoub, J.Meissner, A.Oppelt, S.Rimjaem,
6 G.Vashchenko,S.Weisse, (G.Asova: absent)
7
8 The goal was to give a introduction to Matthias Gross concerning the PITZ
9 TV-system and to discuss an old to-do-list of TV items to clarify what is
10 done and what is still wanted.
11
12 - camera book-keeping and database: works, effort mainly by Axel Hagedorn
13 and Grigorij Vashchenko, unify information (xls-book, data base, ...)
14
15 - extensive SNR analysis and optical information theory (DQE,NEP):
16 not done up to now, topic is mainly noise due to temperatue ==> cooling
17 (at least at beamlet stations)
18
19 - camera cooling: up to now only VC2;
20 not needed for Prosilica, in principle wanted for JAI, improves clearly
21 noise, but our cameras are not suitable and it is expensive, but longer
22 lifetime of cameras is expected;
23 recommendation: buy one camera and test it
24
25 - development of new TV optics, to be done mainly for the matching of new
26 camera type, GV (?) has started calculations
27
28 - remote controlled filter wheels (neutral grey filters): should be
29 installed in all high energy section screens; may also become
30 necessary for long bunch trains (HEDA2);
31 conclusion: a development should be started;
32
33 - improved shielding against stray light (tapered tubes): at several
34 places realised, at several places not necessary. YI will make a list,
35 where it is still necessary (input of Galina necessary).
36
37 - TV tomography: TV system fully mounted, all screens but PSTScr1OTR
38 are aligned and calibrated (PSTScr1OTR is not used until now)
39
40 - TV Heda2: Sakhorn prepares specs with input based on R&D by MM;
41 as far as possible DISP2.Scr1 and DISP3.Scr1 should be similar
42
43 - Camera choice done: yes, test in lab finished, installed now at
44 HIGH1.Scr3 for beam tests; order few afterwards for EMSY, DN stations,
45 maybe DISP (if MAMA can handle the high resolution)
46
47 - additional lenses, changed magnifications: realized at HIGH1.Scr4;
48 further changes proposed for new JAI camera, mainly for beamlet analysis
49 (i.e. Dirk-Naumann stations) and ...?
50
51 - HEDA1 switching optics: done today for implementation of "Scheinpflug"-
52 condition, to be clarified whether a switching optics system with
53 several lenses was already developed
54
55 - systematic improvement of TV optics, a few high quality systems (super
56 system with better resolution / power than others): to be further
57 discussed.
58
59 - tuning of the brightness of LED elements like ring lamps and TV grids:
60 the technical possibility is prepared, but not necessary up to now for
61 TV, only for all streak resolution grids (4 conus boxes).
62
63 - brown lenses: baking to be prepared;
64 Investigate: can other material (quartz) be used ? Laser cleaning ?
65
66 - necessary: roadmap to exchange stepwise analog (old JAI) cameras by
67 digital cameras (Prosilica ?) in ~2012; steps could be:
68 a) after successful tests of JAI BM141 order some of this new type
69 b) replace Prosilicas, e.g. at EMSYs, DN stations, DISPs with JAI BM141
70 c) use freed Prosilicas to replace old JAI
71 d) if wished / necessary, all Prosilicas can be replaced >2012
72
73 - no further open points on the list of JM
74
75 - the use of a ticketing system for trouble shouting at PITZ should
76 furthermore be discussed, especially also for the TV system
77
78 - SW offers the possibility of tests of CCD cameras under radiation
79 conditions (at GSI Darmstadt)
80
81 - There is a request for an instruction for fast and proper adjustment
82 of TV systems
83
84
85 7 Feb. 2011 Juergen Baehr
86 8 Feb. 2011 Anne Oppelt
87 9 Feb. 2011 Galina Asova
88 10 Feb. 2011 Anne Oppelt
89